• Residential Application

  • New Manufactured Homes Require HUD-309 inspections
  • New Manufactured Homes Require HUD-309 inspections







  • Drawings are required prior to the issuance of the permit. Professional drawings complete with a PA Licensed Architect or Engineer seal are only required when the project scope extends beyond the International Residential Code. Depending on the nature of the project, the following table describes what must be included in the drawings.

    Type of Drawing Items to be Included in Drawing

    Site Plan- Structure location on property and distance to other buildings, lot lines, utilities, steep banks, roads, right of ways, etc.
    Foundation- Type and size of all footing, walls, slab, drainage, etc. Note: Frost level is 42” to the top of the footing.
    Floor Plan- (All Levels) Must include all levels – Finished or Unfinished. Include bedrooms, kitchen, bathrooms, windows, doors, decks, etc.
    Framing- Size, length, and spacing of studs, joist, rafters, sheeting, beams, and headers of all levels. Note: All framing lumber must be graded except for projects that do not require a UCC permit. Floor, wall, and roof sheeting does not have to be graded.
    Electrical- Include every circuit location with receptacles, lighting, smoke detectors, and service, and wire sizes and types. Indicate Ground Fault Circuit Interrupters and ARC-Fault.
    Plumbing- Include the location of all fixtures, drain, supply, and vent pipe size, type, and length.
    Mechanical- Include location and type of water heaters, heating, and cooling systems, and ventilation.
    Energy- Include type of insulation and R-value for ceiling, all walls including basement and slab, if needed.
  • Upload a File
    Cancelof
  • Upload a File
    Cancelof
  • Upload a File
    Cancelof
  • By Checking the Box Below I Certify I am the owner or authorized agent of the project for which this application is filed and I Certify that: 1. All information provided on this application is correct and true to the best of my knowledge. 2. The structure will not be used or Occupied until the required Certificate of Occupancy has been issued. 3. This Project will constructed in accordance with the Approved plans and the Uniform Construction Code standards as specified in 34 PA Code Chapter 401-405. 4. No error or omission in either the drawings and specifications or application, whether approved or not, shall permit or relieve me from constructing the work in any manner other than provided for in 34 PA Code Chapters 401- 405.*
  •  
  • Should be Empty: