    INSPECT the external alarm (bell or strobe light) to ensure it clearly indicates the designated building entry point. Inspect to ensure the external alarm label is legible with the word ‘FIRE’ in characters not less than 25 mm in height.
    Press
    Enter
  • 6
    INSPECT the following as applicable: Fire indicator panel (FIP), sub-indicator panel (SIP), repeater panel, fire brigade panel (FBP), mimic panel, fire fan control panel (FFCP) and— (a) ensure that they are clearly visible, readily accessible and free from dust and contaminants; and (b) where a panel is obscured by a door, check that the door is correctly labelled. Where manual call points use replaceable frangible elements, ENSURE that at least one replacement element and tool are available for replacing the element where required.
    Press
    Enter
  • 7
    Where vented batteries are used, INSPECT the battery enclosure for evidence of corrosion.
    Press
    Enter
  • 8
    SIMULATE an alarm condition and confirm that all required common or general visual and audible indications operate and the external alarm is activated. Where the system is monitored ensure the alarm has activated the alarm signalling equipment. Where CIE is a subindicator panel, confirm that the alarm condition is indicated at the FIP.
    Press
    Enter
  • 9
    SIMULATE an alarm and confirm the alarm initiates the occupant warning system including any visual warning devices (VWD).
    Press
    Enter
  • 10
    INITIATE an isolate/disable condition at the fire indicator panel and confirm that all required common or general visual and audible indications operate. Where the system is monitored, ensure the isolate is received by the monitoring service provider alarm signalling equipment. Where the panel is an SIP, confirm that the isolate/disable condition is indicated at the FIP as either a fault or isolate/disable.
    Press
    Enter
  • 11
    TEST the operation of each filament type visual indicators.
    Press
    Enter
  • 12
    INSPECT zone block plans to ensure that they are securely mounted and legible and supplementary zone drawings, where required, are available and legible.
    Press
    Enter
  • 13
    CHECK that baseline data is available and legible.
    Press
    Enter
  • 14
    Press
    Enter
  • 15
    • Huge
    • Large
    • Normal
    • Small
    Ok
    quoteCreated with Sketch.
    Ok
    Press
    Enter
  • 16
    Drag and drop files here
    Select files to upload
    Max. file size: 10.6MB
    Cancelof
    Press
    Enter
  • 17
    Clear
    Press
    Enter
  • Should be Empty:
Question Label
1 of 17See AllGo Back
close