1.) All construction work on any project must be completed within six
months of commencement. This period may be extended to twelve months with
the approval of the Board of Directors.
2.) Prior to the commencement of construction, an anticipated project
timeframe indicating the start date and that of Final Completion. Please be
reminded of the permitted construction period in terms of the Rules of
Bendor Village.
3.) Should the sidewalk be utilised for the storage of building materials,
a refundable deposit R5,000.00 is payable as mentioned above.
4.) Proof that your neighbours in the immediate vicinity have been notified
of the intended construction works and the intended timeframe.
5.) That the construction workers need to be registered with the security
for this project.
6.) Reminder of the permitted construction working hours permitted, Monday
to Friday from 07H00 to 17h00. Work on weekends and public holidays are not
permitted.
7.) It is your responsibility as the Owner to ensure that your contractors
comply to the minimum Health and Safety Regulations and the prevailing COVID
Regulations as Gazetted by the National Government from time to time.
8.) The site and building area must be fenced with shade net in a neat and
secure manner before any construction works commences. (See attached
specifications)