IPC Project Inspection Checklist
Project
Date
-
Month
-
Day
Year
Date
Location
Inspector
Email
example@example.com
Position
Project Manager
Field Manager
General Requirements and Postings - CFR 1926 Subpart C & D
Rows
Yes
No
N/A
1. 1st aid kit on site and stocked? 1926.50(d)(2)
2. 1st aid kit readily accessible? 1926.50(d)(1)
3. Emergency phone numbers posted? 1926.50(f)
4. OSHA & employment posters in place and visible?
5. OSHA 300A Summary posted? (Feb 1 - April 30 only) 1904.32(b)(6)
6. IPC Safety Bill of Rights posted?
7. IPC Management Commitment posted?
8. Emergency action plan posted? 1926.35(a)
9. Field Manager &/or designated person is certified in 1st Aid/CPR 1926.50(c)
10.Field Manager has OSHA 30
11.Is there a copy of the IPC Safety Manual on site?
12.Is there a copy of the IPC HAZCOM manual onsite that is GHS compliant? 1926.21(b)(3)
13.Are SDS/MSDS & chemical inventory up to date & current for the project? 1926.21(b)(3)
14.Do all employees have an IPC Safety Training Card on their person?
Comments
Safety Expectations - CFR 1926 Subpart C
Rows
Yes
No
N/A
1. Is a copy of the pre-con Job Hazard Analysis on site and have all employees reviewed it? 1926.21(b)(2)
2. Are weekly toolbox safety meetings being performed before work on the first day of the work week and documented?
3. Are Daily Job Briefing being performed and documented? Verify pre-task JSA’s matches work observed and employees have signed off.
4. Do employees understand their STOP WORK Authority?
5. Is there documentation of all employees being given a Jobsite Orientation?
Comments
Working on or near exposed energized parts. 1910.269(I)
Rows
Yes
No
N/A
1. Are lines or equipment being worked de-energized when possible?
2. Are only “Qualified” employees being allowed to work on energized lines?
3. Are at least two employees present when energized work is performed?
4. Are trucks grounded when being used for energized work?
5. Is there sufficient amount of cover-up available? Are proper cover-up procedures being followed?
6. Rubber gloves and sleeves being worn inside of approach distance?
7. If de-energizing lines, are opens visual?
8. If de-energizing lines, are lines being tested before grounds are installed?
9. If grounds are installed are they equipped with ground flags?
10. If lines are grounded are “Men Working on Line” pole wraps installed?
11.Are employees working on the ground wearing rubber gloves if setting poles near energized lines?
Comments
Fall Protection/PPE 1910.269 (g)
Rows
Yes
No
N/A
1. Fall protection being used if needed or required?
2. Training been performed and documented? Check training cards
3. Fall protection equipment inspected before use each time? Verify with employees to see if they know how to perform inspection
4. Is climbing gear being inspected before each use?
5. Are climbing hooks being put on and taken off at the bottom of the pole?
6. All employees wearing safety glasses?
7. All employees wearing leather work boots above ankle?
8. Are all employees wearing gloves?
9. Employees wearing cut resistance gloves/Kevlar sleeves when stripping wire?
10. All employees wearing hardhats?
11. Are all employees wearing high-vis outerwear?
12. Are employees doing energized work wearing FR clothing?
13. Face shields/hearing protection being used while using a chainsaw?
Comments
Mechanical Equipment 1910.269(p)
Rows
Yes
No
N/A
1. Are trucks equipped with reverse audible alarms?
2. Are trucks only backed up when a designated employee signals to do so?
3. Are all vehicles/trailers properly licensed? Are all DOT annual inspections within the last 12 months?
4. Are outrigger pads being used on all outriggers?
5. Are outriggers being fully retracted before trucks are moved?
6. Are employees maintaining the 3-point rule while ascending and descending trucks?
7. Are trucks free from excessive debris and material?
8. Have employees received IPC training? Check training cards 1926.1060(a)
9. Are chock blocks being used on all trucks?
Comments
Hand and Portable Power Tools - 1910.269 (i)
Rows
Yes
No
N/A
1. Are all power tools equipped with proper guards? 1926.300(b)(1)
2. Are electrical cords and plugs in proper working order? 1926.300(a)
3. Power tools either grounded or double insulated? 1926.302(a)(1)
4. Are tools being inspected and properly stored? 1926.300(a)
5. If required, are power tools being operated using 2 hands?
Comments
Live-Live Tools - 1910.269 (j)
Rows
Yes
No
N/A
1. Is each live-line tool whipped clean and visually inspected for defects before each use each day?
2. Has each live-line tool on the project been sent in for testing within the last two years?
3. Are Live-line tools properly stored when not in use?
Comments
Overhead Lines - 1910.269 (q)
Rows
Yes
No
N/A
1. Are poles being hauled properly, (secured and flagged)?
2. When conductors are being strung is the rolling ground in use?
3. Are employees protected from falling objects?
4. Is reel handling equipment, including pulling and tensioning equipment in safe operating condition, leveled and aligned?
5. Are stringing lines, pulling lines, conductor grips, load-bearing hardware and accessories, rigging, and hoist being used within their load ratings.
6. Is there reliable communications, through two-way radios or other equivalent means, between the reel tender and the pulling rig operator?
7. Are energized conductors being strung over or near properly covered or protected.
8. Are all nylon and chain setting slings in compliance?
Comments
Confined Space - CFR
Rows
Yes
No
N/A
1. Has space been tested for quality of air? 1910.146(d)(5)(iii)
2. Is all required PPE in place? 1910.146(d)(4)
3. Communication established between entrants/attendant? 1910.146(d)(4)(iii)
4. Is there site specific procedures or requirements?
5. Is the competent person present? 1910.146(b)
6. Are required permits completed? 1910.146(f)
7. Is the emergency action plan posted? 1926.35(a)
8. Is LOTO being used? 1910.147
9. Are entrants and attendants properly trained? Check training cards 1910.146(g)(1)
Comments
Aerial Lifts and Platforms
Rows
Yes
No
N/A
1. Are employees trained/certified on equipment? Check training cards
2. Are employees remaining on the platform at all times?
3. Are all safety devices operational?
4. Have bucket trucks been die-electric tested within the last 12 months?
5. Are employees running the lower controls as part of their daily inspection?
6. Are daily inspections being performed?
Comments
Housekeeping and Material Handling - CFR 1926 Subpart C
Rows
Yes
No
N/A
1. Are stairways and aisles clear of obstructions? 1926.25(b)
2. Are materials properly stored or stacked? 1926.25
3. Are pipes/conduit blocked to prevent rolling? 1926.25
4. Are nails removed or bent over? 1926.25(a)
5. Are employees using proper lifting techniques? 1926.20(b)(1)
6. Is their adequate material handling equipment on the job?
7. Any small pieces of conduit or flex on walking or working surfaces? 1926.25(a)
Comments
Special Conditions - 1910.269 (w)
Rows
Yes
No
N/A
1. Are signs and barricades used to protect the public? 1926.200
2. Are signs and barricades adequate? 1926.200
3. If flaggers are needed are they trained?
4. Are open holes covered and barricaded if left unattended?
Comments
Add Photos to Report
Take Photo
Take Photo
Take Photo
Take Photo
Take Photo
Take Photo
Upload Photo
Upload Photo
Upload Photo
Upload Photo
Upload Photo
Upload Photo
Signatures & Submission
Inspector Signature
Date
/
Month
/
Day
Year
Date
Preview PDF
Submit
Should be Empty: