• Start-Up Request Form

  •  / /
    Pick a Date
  •  
  •  
  •  
  •  
  • Required Preparations

    General

    1. All control components (including controllers, sensors, touchscreens, switches, etc.) have been installed, powered up, and tested to be functioning correctly.
    2. All categorey cabling has been tested for polarity and continuity and is functioning properly.
    3. All analog, 0-10V, DMX, and other necessary control wiring has been tested for polarity and contunity and is functioning properly.
    4. Installing contractor familiar with the installation will be available with all tools/equipment necessary to access and troubleshoot all system components.
    5. ALL serial numbers and locations for networked devices have been recorded for programming purposes.
    6. A sequence of operation shall be on site detailing system function and integration function with other networked systems.
    7. Scene selection has been identified and approved by an owners representative and is included as a suppliment to sequence of operation.
  • Additional Charges
    PLEASE NOTE THAT IF A RETURN TRIP OR ADDITIONAL TIME IS REQUIRED TO COMPLETE SYSTEM START UP DUE TO SYSTEM NOT BEING PREPARED TO START UP (INCLUDING SYSTEM INTEGRATION CONTRACTORS NOT BEING PREPARED FOR START UP) OR INCORRECT INSTALLATION OF PRODCUTS MAY RESULT IN ADDITIONAL CHARGES. ADDITIONAL WORK WILL REQUIRE A PURCHASE ORDER PRIOR TO PROCEEDING.

     

  •  / /