• Alpena County Erosion Control Permit Fee Schedule

  • Transportation Facilities
    To include but not limited to: streets, highways, roadways -public/private, trails and paths.

      Plan Review Permit Fee Total
    Up to½ mile Included  $180.00 $180.00
    Disturbance of½ mile Included $210.00 $210.00
    Each additional½ mile or fraction  thereof Included $ 70.00  $ 70.00

    Industrial/Commercial Development
    Review fees included in permit fee along with 3 inspections included in fee.

    Up to one acre Included $280.00 $280.00
    Each additional acre Included $110.00 $110.00

    Commercial projects, greater than one acre, require sealed, engineered site plans with runoff calculations, and either a signed letter of acknowledgment or a letter of credit. If the inspector feels that it is necessary to have a professional engineer review the plans submitted to the County, all review costs will be paid for by the developer.

    Utility and Corridor Development
    To include but not limited to: underground cables, above ground major transmission cables, water mains and sewers.

    Minimum Permit Fee Included $280.00 $280.00
    0-3 feet wide disturbance $ 0.04 $ 0.04 $ 0.08
    4-10 feet wide disturbance $ 0.05 $ 0.05 $ 0.10
    >IO feet wide disturbance $ 0.07 $ 0.07 $ 0.14

    Gravel and Sand Pit Excavation
    To include any open pit greater than one acre in size, active or inactive. Generally a five year permit may differ if a signed agreement is made with the agent in advance.

    Sand/Gravel Pit $175.00 $50.00 X 5 $425.00

     Waterway lmpoundment Construction or Improvements
    To include but not limited to: ponds, seawalls, rip rap, etc.

    Up to one acre Included $180.00 $180.00
    Disturbance of one acre Included $210.00 $210.00
    Additional acre or fraction thereof Included $ 70.00 $ 70.00

    Septic Systems
    To include septic system installation, replacement or repair not associated with other earth change activities.

    Septic System Included $180.00 $180.00

    Residential Construction and Miscellaneous Earth Changes
    To include all single family dwellings, additions, barns, garages and subjects not covered by or within the above categories. 3 inspections included in fee.

    Up to one acre Included $180.00 $180.00
    Each additional acre Included $ 85.00 $ 85.00

    * Additional Site Inspections for any permit, beyond three, will be charged at a rate of $70.00 per visit and will be billed to the landowner at the expiration of the permit. Any projects, one acre or larger, with a storm water collection, or discharge point may require a storm water operator for the duration of the project. Any project five acres or larger shall require a certified storm water operator for the duration of the project.

    MAKE CHECK PAY ABLE TO: Alpena County Treasurer

    CommissionasH.istory,.Soil Erosion2022Erosion Fee Schedule
    Updated 01.27.22 llb

  • PERMIT APPLICATION (For Part 91)
    SOIL EROSION AND
    SEDIMENTATION CONTROL
    Alpena County Soil Erosion
    720 W. Chisholm Street Suite 3
    Alpena, MI 49707
    989-354-9534

     

  • 2.  LOCATION

  • 3.  PROPOSED EARTH CHANGE

  •  - -
  •  - -
  • 4.  SOIL EROSION AND SEDIMENTATION CONTROL PLAN (Refer to Rule 323.1703)

  • 5.  PARTIES RESPONSIBLE FOR EARTH CHANGE

  • 6.  PERFORMANCE DEPOSIT (If required by the permitting agency)

  • I (we) affirm that the above information is accurate and that I (we) will conduct the above described earth change in accordance with Part 91, Soil Erosion and Sedimentation Control, of the Natural Resources and Environmental Protection Act, 1994 PA 451, as amended, applicable local ordinances, and the documents accompanying this application.

  • Clear
  •  - -
  • Clear
  •  - -
  • *Designated agent must have a written statement from landowner authorizing him/her to secure a permit in the landowner's name.

  • Alpena County logo



  • I,*the land owner agrees to authorize

          

    the to act as my authorized agent for the submittal of the Soil Erosion &

    Sedimentation Control Permit application for my earth change activities. Further, I

    agree that modifications made to the application by the County Enforcing Agent may

    be approved and signed for the aforementioned authorized agent upon receipt of the

    Soil Erosion & Sedimentation Control Permit. I acknowledge that, as the legal

    landowner, lam responsible for the earth change activities occurring on my site.

  • Clear
  •  - -
  • Alpena County logo
  • GENERAL CONDITIONS:

  • In accordance with Rule 1709 promulgated under the authority of Part 91, Soll Erosion and Sedimentation Control, of the Natural Resources and Environmental Protection Act, 1994 PA 461, as amended, and in addition· to the information on the attached plan(s) and special conditions, the following general conditions apply to the earth change authorized by this permit:

    • Design, construct, and complete the earth change in a manner that limits the exposed area of disturbed land for the shortest period of time.

    • Remove sediment caused by accelerated soil erosion from runoff water before it leaves the site of the earth change.

    • Temporary or permanent control measures shall be designed and installed to convey water around, though, or from the earth change at a non-erosive velocity.
    • Install temporary soil erosion and sedimentation control measures before or upon commencement of the earth change activity and maintain the measures on a daily basis. Remove temporary soil erosion and sedimentation control measures after permanent soil erosion measures are in place and the area Is stabilized. ('Stabilized" means the establishment of vegetation or the proper placement, grading, or converting of soil to ensure Its resistance to son erosion, sliding, or other earth movement).

    • Complete permanent soil erosion control measures for the earth change within five calendar days after final grading or upon completion of the final earth change. If It Is not possible to permanently stabilize the earth change, then maintain temporary sol! erosion and sedimentation control measures until permanent soil erosion control measures are in place and the area is stabilized.
  • DEQ Logo
  • Michigan Department of Environmental Quality

    Part 91, Soil Erosion and Sedimentation Control Plan

  • Minimum Requirements

  • Rule 1703 Requirements

  • Map with scale: 1” = 200’ or less, or indication of exact distances between noted features on site plan, including site location sketch

  • Legal description of property (town, range, section, quarter-quarter section)

  • Proximity of any proposed earth change to lakes and/or streams

  • Predominant land features

  • Slope description or contour intervals

  • Soils survey or written description of the soil types of the proposed exposed land area

  • Description and location of the physical limits of each proposed earth change

  • Description and location of all existing and proposed on-site drainage and dewatering facilities

  • Timing and sequence of each proposed earth change

  • Location and description for installing and removing all temporary SESC measures

  • Description and location of all proposed permanent SESC measures

  • Maintenance program for all permanent SESC measures and designation of person responsible for maintenance

  • *If No is checked above, the plan must be revised to include the missing element prior to submittal/approval.

  • Alpena County logo
  • APPROXIMATE PROJECT TIMING: (Month/Year)

  • MINOR PROJECTS:

  • MAJOR PROJECTS:

  • Site Plan (timing/sequence date)
    Checklist:

  • SITE SEQUENCE TABLE

  •  Briefly describe the maintenance plan (include responsible party) for each temporary and permanent SESC measure.

  •  - -
  •  - -
  • Construction Sequence

    Temporary SESC Measures Installed

  • Permanent SESC Measures Installed

  • Briefly describe the maintenance plan (include responsible party) for each temporary and permanent SESC measure.

    Silt Fence

  • Buffer Strips

  • Catch Basins/Inlets

  • Street Sweeping

  • Seeding/Mulch

  • Storm Ponds/Sediment Basins

  • Alpena County logo
  • Silt Fence:

    • Temporary sediment control measures

    • Use for sheet flow, not concentrated flows

    • Place adjacent to sensitive areas

    • Place at or beyond base of slope

    • Place on the same contour

    • Trench in 6 inches

    • Use multiple rows up the slope

    • Use support fence if necessary

    • DO NOT place in streams or ditches

    • MAINTAIN - remove accumulated sediment

    • Remove after site is permanently stabilized