2025 Daily Report
  • Daily Report Guidelines 

    1. Upload a Job Safety Analysis to the daily report. (JSA must be on every daily report)
    2. Upload Photos (minimum of 5) - must be clear.
      • Close up Photos of electrical gear installed. 
      • With the dead front off and panel door open
      • Showing the panel schedule
      • Show all screws are present on the Panel Cover
    3. Pictures from 10-15 feet back (For Perspective; ie… site cleanliness, no trip hazards, work accomplished...).
      • If Trenching, show photos of depths with a tape measure.
      • Concrete pads (show the stub up location and quality of the concrete finish)
    4. Side profile pictures of the EV Installation.
      • Showing uniformity and alignment.
      • If outdoors, compiles with its weatherproof rating.
    5. Clear Pictures of chargers with wire terminations and what charger is dialed to (front cover removed).
      • Showing that the circuits are labeled and that insulation has been stripped correctly.
      • Rotary dial settings
      • Clear pictures of the front cover clearly showing Charger IDs and Endpoints. 
    6. Pictures 10-15 feet back showing the entire parking space w/ pedestal chargers, signs, and stenciling.
      • Show where the pedestal is mounted in respect to the parking stripe line.
    7. Pictures showing conduit, rigid pipes, and uni-strut level/plum.
    8. Torque Specs, voltage tested, duct seal.
    9. Labeling: Panel, Step down, Disconnect, Meter, Chargers, Branch wire.
      • Panel Schedule with a label maker. 
    10. Pictures showing any obstacles. 
  • 2025 Daily Report

  •  - -
  • Browse Files
    Drag and drop files here
    Choose a file
    Cancelof
  • Should be Empty: