REVENT CHECKLIST
  • REVENT CHECKLIST

  • Water Heater Backing 4' & 6' centered*
  • Pedestal backing centered at 33"*
  • Tub drains are tight*
  • Shower drain tight & stubbed above gasket*
  • Toilet in slab - correct distance of back and side wall*
  • Stud guards done and checked*
  • Kit sink drain at 16"*
  • Pedestal drain 15 1/2 - 16 1/2" off side 2x4 wall*
  • Pressure regulator installed if needed*
  • Water svc capped at the street and tested with air*
  • Stud shoes & structure plates installed with galvanized nails*
  • Hose bibs installed & correct distance off plywood if brick or flush for vinyl*
  • Gas installed and tested*
  • Sleeve for gas line installed (1 1/2" pvc) if it is a brick home*
  • Washer box installed at 3' to the bottom of the box (not taller)*
  • Shower valves installed between (3'6" & 4') - nothing higher or lower unless specified*
  • Shower heads centered on valve and board rigid*
  • Water lines through slab at least 1' tall at lavs and kit sink*
  • Tub spent straight & has wood with nail on to make rigid for tub spout*
  • Tiled shower tub spout has sliver bracket to brace for tub spout*
  • Tankless WH hot/cold spaced 7 1/2" apart & stubbed out 10" past drywall*
  • Should be Empty: