  • HOT-WORK PERMIT

    HOT-WORK PERMIT

    Hot Work Procedure HSEOP-10-02
  • Seek an alternative/safer method if possible!

    This Hot-Work Permit is required for any operation that involves burning, welding, using an open flame, fire- or spark- producing tools, or that produces a source of ignition.  This work includes, but is not limited to: welding, brazing, cutting, grinding, soldering, thawing pipe, torch-applied roofing, and chemical welding.

  • Date*
     / /
  • THIS PERMIT IS GOOD FOR 24 HOURS

    Review the checklist items below, and select the best answer regarding your hot-work.
  • 1. Available sprinklers, hose streams, and fire extinguishers are in service and operable.*
  • 2. Hot-work equipment is in good working condition in accordance with manufacturer’s specifications.*
  • Requirements within 35 ft. (11 m.) of hot work:

  • 3. Flammable liquid, dust, lint, and oily deposits have been removed.*
  • 4. Explosive atmosphere in area is eliminated. LEL measured at*
  • 5. Floors are swept clean and trash has been removed.*
  • 6. Combustible floors have been wet down or covered with damp sand, fire-resistant/non-combustible material, or equivalent.*
  • 7. Workers are protected from electrical shock when floors are wet.*
  • 8. Other combustible storage material have been removed or covered with listed or approved materials (welding pads, blankets, curtains, fire-resistant tarpaulins), metal shields, or non-combustible materials.*
  • 9. All wall and floor openings have been covered.*
  • 10. Ducts and conveyors that might carry sparks to distant combustible materials are covered, protected, or shut down.*
  • Requirements for hot work on walls, ceilings, or roofs:

  • 11. Construction is non-combustible and without combustible coverings or insulation.*
  • 12. Combustible material on other side of walls, ceilings, or roofs are moved away from hot-work.*
  • Requirements for hot work on enclosed equipment:

  • 13. Enclosed equipment is cleaned of all combustible materials.*
  • 14. Containers are purged of flammable liquid/vapor.*
  • 15. Pressurized vessels, piping, and equipment are removed from service, isolated, and vented.*
  • Requirements for hot-work fire watch and fire monitoring.

  • 16. Fire watch is provided during, and for a minimum of 30 min. after hot work, including break activity.*
  • 17. Fire watch is provided with suitable fire extinguishers and, where practical, a charged small hose.*
  • 18. Fire watch is trained in use of equipment and in sounding alarm.*
  • 19. Fire watch can be required in adjoining areas, above and below.*
  • 20. As per the PAI/fire watch, monitoring of hot-work area has been extended beyond 30 min.*
  • Signatures

  • I verify that the above location has been examined, the precautions marked on the checklist above have been taken, and permission is granted for this work.
  • Click "Submit" to send hot work permit to Permit-Authorizing Individual (PAI) for approval/signature.