What is the minimum legal height for the main guardrail on a scaffold working platform?
910mm
950mm
1000mm
How often must a scaffold be inspected by a competent person under statutory regulations?
Every 7 days
Every 14 days
Every 28 days
What is the primary purpose of a toe board on a scaffold platform?
To provide a footrest for workers
To prevent materials, tools, and debris from falling off the edge
To strengthen the overall scaffold structure
What is the correct angle (or ratio) for a leaning ladder used for access to a scaffold?
1 unit out for every 3 units up (75 degrees)
1 unit out for every 4 units up (75 degrees)
1 unit out for every 5 units up (75 degrees)
Who is legally permitted to alter, modify, or dismantle a scaffold on site?
Any site worker who has attended a morning safety briefing
The site manager or health and safety officer
A trained and competent scaffolder
What does a red 'Scafftag' (or a scaffold with no tag present at the access point) indicate?
The scaffold is safe to use but requires extra caution
The scaffold is unsafe, incomplete, or condemned, and MUST NOT be used
The scaffold is reserved specifically for bricklayers and masons
What is the minimum required height for a toe board on a working platform?
100mm
150mm
200mm
What is the maximum allowed gap between any guardrail and toe board (or between intermediate and top guardrails)?
200mm
350mm
470mm
What should you do if you notice a loose, damaged, or missing scaffolding board on a working platform?
Try to kick it back into place and continue working
Ignore it if it is not in your immediate working area
Do not attempt to fix it; report it to the site manager or scaffold supervisor immediately
When must an additional scaffold inspection take place outside of the standard 7-day cycle?
After any adverse weather conditions (e.g., high winds, heavy snow) or modifications
Every time a new trade or sub-contractor starts working on the site
Immediately after a large delivery of building materials arrives on site
What is the correct protocol for supporting scaffold base plates on uneven or soft ground?
Base plates can be supported by stacking building bricks or blocks
Base plates must be supported by proper timber sole boards to distribute the load
Base plates do not need support if the scaffold is tied to the building
When working on a scaffold, where should materials and tools be stored?
Neatly away from the edge, leaving a clear and unobstructed walkway for access
Stacked as high as possible against the guardrails to save space
Left anywhere on the platform as long as they belong to your team
What Other Courses Are You Interested In?
*
Legionella Awareness
Mental Health Awareness
Fire Extinguisher Awareness
Fire Extinguisher Inspection
Ladder Safety Awareness
Ladder Safety Inspection
PPE
Hot Work
HAVS
Health & Safety For Employees
Health & Safety For Managers
Fire Safety For Employees
Harness & Lanyard Inspection
Harness & Lanyard User Checks
Face Fit Testing
Excavation Course
Demolition Safety
Scaffolding Safety
Scaffolding Tag
Please Select
Pass Scaffolding Awareness
To join our mailing list & agree to our privacy policy opt-in below: https://healthandsafetytraining1st.co.uk/privacy-policy/
*
I agree
Please verify that you are human
*
CalculationCorrection
Submit
Score
Should be Empty: