• FRM-AC01 - Application for Concession from CLOCS-A Standard

    FRM-AC01 - Application for Concession from CLOCS-A Standard

  • 1. Applicant Details

  • Date
     - -
    2 digit day, 2 digit month, 4 digit year
  • Format: 0000 000 000.
  • 2. Vehicle Details

  • Vehicle Type
  • Browse Files
    Drag and drop files here
    Choose a file
    Cancelof
  • 3. Concession

  • This application seeks approval for a concession from CLOCS-A Standard requirements for the above vehicle/operator due to the nature of the vehicle's use, body design, limited frequency of access and assessed risk profile.

    The application is submitted in accordance with the CLOCS-A Standard, which requires the Client and Principal Contractor to determine applicability based on project risk and make a reasonable determination regarding which heavy vehicle transport activities fall within the scope of CLOCS-A requirements.

  • Concession type. Please select*
  • 4. Reason Compliance Cannot Reasonably Be Achieved

  • Provide a detailed explanation of why compliance with the requirement cannot reasonably be achieved.

    Include:

    • Technical limitations
    • Vehicle design constraints
    • Operational constraints
    • Manufacturer limitations
    • Regulatory conflicts
    • Temporary circumstances
  • 5. Basis for Concession Request

  • A. Low Frequency of Access

  • The vehicle is expected to access the project site on an infrequent basis*
  • This form applies to frequent heavy vehicle operations as including operators making six or more round trips to a construction project site within a 12‑month period.

  • B. Specialist Vehicle Type

  • The vehicle performs a specialist function and is not involved in routine construction logistics activities such as:

    • soil removal;
    • material deliveries;
    • concrete transport;
    • plant haulage;
    • repetitive site servicing operations.
  • C. Limited Community Exposure

  • The vehicle (please select):
  • 6. Description of Proposed Alternative Controls

  • Describe the alternative controls proposed to achieve the intended safety outcome.

  • 7. Alternative Controls Implemented

  • Notwithstanding the requested concession to the CLOCS-A requirements, the following controls will remain in place. Please select:
  • Browse Files
    Drag and drop files here
    Choose a file
    Cancelof
  • 8. Exposure Assessment

  • Complete all applicable fields.*
  • 9. Risk Assessment Summary

  • A project transport risk assessment has been undertaken considering. Please select:
  • Risk Outcome

    Download and complete the Human Impact Route Assessment (‘HIRA’) tool to determine the overall residual risk rating, then upload the completed assessment as part of your application.

  • Browse Files
    Drag and drop files here
    Choose a file
    Cancelof
  • 10. Risk Assessment

  • Identify hazard. Examples include:

     

    • Limited driver visibility
    • Absence of specific CLOCS-A safety technology
    • Increased reversing exposure
    • Vulnerable road user interaction
    • Site congestion
    • Vehicle manoeuvrability limitations

     

  • Step 1 - Identify Hazard*
  • Step 2 - Inherent Risk Assessment. Assess risk before additional controls (refer to Resources - CLOCS-A Risk Assessment Criteria to calculate Risk Rating)*
  • Step 2 - Inherent Risk Assessment. Assess risk before additional controls
    Rows
  • 3 - Alternative Controls Assessment*
  • Step 4 - Residual Risk Assessment. Assess risk remaining after implementation of proposed controls (refer to Resources - CLOCS-A Risk Assessment Criteria to calculate Risk Rating).*
  • Step 4 - Residual Risk Assessment. Assess risk remaining after implementation of proposed controls
    Rows
  • Residual Risk Assessment

  • Overall residual risk following implementation of alternative controls (please select):
  • Resources

    CLOCS-A Risk Assessment Criteria.

     

  • 11. Safety Outcome Assessment

  • 12. Request

  • We request approval for this vehicle/operator to have a concession to the requirements of the CLOCS-A Standard while continuing to comply with all site, transport, safety and regulatory obligations based on (please select):
  • 13. Assessor Findings

  • Documentation Review (Please select)
    Rows
  • 14. Assessor Recommendation

  • Based on the information provided and assessment undertaken, the Assessor recommends:*
  • Recommended Review Period
  • 15. TG1 Review

  • TG1 Members Participating*
  • Conflict of Interest Declaration

  • Have all participating TG1 members declared actual, potential or perceived conflicts of interest?
  • 16. TG1 Decision

  • TG1 Meeting Date*
     - -
    2 digit day, 2 digit month, 4 digit year
  • Following review and consideration of the information provided, TG1 determines:*
  • Approval Effective Date*
     - -
    2 digit day, 2 digit month, 4 digit year
  • Approval Expiry Date*
     - -
    2 digit day, 2 digit month, 4 digit year
  • Review Date*
     - -
    2 digit day, 2 digit month, 4 digit year
  • 17. Monitoring Requirements

  • The following monitoring activities are required:
  • 18. Concession Register Entry

  • Approval Date
     - -
    2 digit day, 2 digit month, 4 digit year
  • Review Date
     - -
    2 digit day, 2 digit month, 4 digit year
  • Expiry Date
     - -
    2 digit day, 2 digit month, 4 digit year
  • 19. Appeal Rights

  • The Applicant may request review of this decision by submitting additional supporting evidence to TG1 within thirty (30) calendar days of notification.

    Appeals must identify:

    • The grounds for review.
    • New or additional evidence.
    • Any factual inaccuracies in the original assessment.
  • 20. Authorisation

  • Authorisation*
  • Risk Assessment Guidance

  • TG1 should generally be satisfied that:

    • Compliance is not reasonably practicable.
    • Alternative controls are clearly defined.
    • The intended safety objective of the CLOCS-A requirement is maintained.
    • Residual risk is Low, Moderate, or otherwise demonstrably acceptable.
    • The concession does not create an unreasonable increase in risk to vulnerable road users.
    • Conditions, review periods and monitoring requirements are clearly documented.

    TG1 should not approve a concession where the proposed alternative controls fail to maintain the intent of the CLOCS-A requirement or where residual risk remains unjustifiably high.