PROJECT SCOPE MANAGEMENT
1. The project plan provides a baseline for several things. Which one of the following does the project plan not provide a baseline for?
Please Select
A. Scope
B. Cost
C. Schedule
D. Control
2. Which of the following can best help a project manager during project execution?
Please Select
A. Stakeholder analysis
B. Change control boards
C. PMIS
D. Scope verification
3. You are the project manager for your organization. When it comes to Integrated Change Control, you must ensure which one of the following is present?
Please Select
A. Supporting detail for the change exists
B. Approval of the change from the project team
C. Approval of the change from an SME
D. Risk assessment for each proposed change
4. You are the project manager for your organization. Management would like you to use a tool that can help you plan, schedule, monitor, and report your findings on your project. This tool is which one of the following?
Please Select
A. PMIS
B. EVM
C. Status Review Meetings
D. Project team knowledge and skill set
Which of the following processes happen in the correct order?
Please Select
A. Scope planning, activity definition, activity duration estimating, cost budgeting
B. Scope planning, resource planning, activity duration estimating, activity sequencing
C. Scope definition, scope planning, activity definition, activity sequencing
D. Scope planning, scope definition, activity definition, activity sequencing