BTQ STEAM are managed by our own YTL Development members, we receives and process request work orders daily. Our overall goals are to schedule and complete these request in a timely manner. In order to perfect our goals, each Job request must be specified clearly in the form provided so we can decided on the time-frame.
Which Time Frame to choose??
NORMAL - Choose this option if the Job is not "CRITICAL" and there are no effect with development and production for more than 1- 3 Months;
- Master Plan (3 Months)
- Rock Face Design (2 Months)
- Site Investigation - Resistivity Test on Greenfield (1 Month)
- Topo Survey (1 Month)
URGENT - Choose this option if the Job if the JOB is under the planning for the next development phase and would have effect on our production in less than 2 - 4 Weeks;
***SURVEY DATA MUST BE PROVIDED***
- Site Investigation - Resistivity Test on Developed Area/ Rock Face (2 Weeks)
- Rock Face Design - (2 Weeks)
- Volume Analysis - (2 Weeks)
VERY URGENT - Choose this option if the job is "CRITICAL" and is effecting our development and production plan is less than 3 Days.
***SURVEY DATA MUST BE PROVIDED***
- Volume Analysis - (3 - 7 Days)
- Vector (Google Map file - KMZ KML) - (3 Days)
- Data Request ( .dxf .dwg .dtm. str file ) / Others
Time Frame of the Job Request are subjected to the urgency of the job. Every request will be dealt based on the time frame submitted. Jobs that are requested under Urgent & Very Urgent must be attached with the updated survey file by the applicable quarry engineer upon submitting the request, Failure to do so, the JOB Request will be REJECTED.
Thank you in advance for your cooperation.